Adjust report sending

  • October 18, 2018
  • 3 replies
  • 1291 views

Situation: I set up a report in Adobe.  The way I set it up is to send a 90 day report to our team once a week (PDF).  After talking to the team, we decided it would be more beneficial to view a 7 day report once a week, and then a 90 day report once a month.

Question: Do you know how to modify the report sending?

Other info in case you need: The way I set up the report was: AAWorkspace/create report/share/send file on schedule/PDF/Frequency: Send weekly; Send every 1 week; SEND ON SCHEDULE... I inputted each person's email address into the box... Soooo, I don't know how to get back there to adjust the schedule.

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by Gigazelle

Yes, Go to Components > Scheduled Projects. You can locate the project and adjust the schedule from there.

3 replies

Gigazelle
Employee
December 17, 2018

Thanks Max! Glad it worked for you.

maxb90314051
New Participant
December 17, 2018

Thanks this works! The OP should make this as the answer

Gigazelle
GigazelleAccepted solution
Employee
October 23, 2018

Yes, Go to Components > Scheduled Projects. You can locate the project and adjust the schedule from there.