API Segment update would be applied on Calculated Metric? | Community
Skip to main content
New Participant
Jun 27, 2022 5:15 AM UTC
Solved

API Segment update would be applied on Calculated Metric?

Hi, I have one question regarding API work using updated Calculated metrics & Segments

For example, 

1) Make Calculated Metric A on May 1st, using Segment B

2) Update Segment B on May 5th

3) Extract Data through API utilizing Calculated Metric A on May 7th

 

-> In this case, would extracted data automatically apply Segment B's update?

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
leocwlau
leocwlauAccepted solution
New Participant
Jun 27, 2022 7:03 AM UTC

I didn't test and wondering if Adobe has any documentation for this specific requirement. However, my understanding of segments and calculated metrics is that they are both evaluated with live data upon consumption, so the answer to your question should be yes, the updated segment will be used on May 7th.

3 replies

leocwlau
leocwlauAccepted solution
New Participant
Jun 27, 2022 7:03 AM UTC

I didn't test and wondering if Adobe has any documentation for this specific requirement. However, my understanding of segments and calculated metrics is that they are both evaluated with live data upon consumption, so the answer to your question should be yes, the updated segment will be used on May 7th.

Translate
Jennifer_Dungan
Level 2
Jun 27, 2022 11:14 PM UTC

I agree, since the segments and calculated metrics update to all reports and are evaluated live, any changes you make will apply to new API calls.

 

This is good, but can also be bad.. if you need a variation of your segment or calculated metric, always make sure to do so in a copy so that all the existing processes using the original remain untouched.

Translate
JS00101Author
New Participant
Jun 28, 2022 1:22 AM UTC

Thank you for replying to both of you 🙂 

Translate