hi team, 

 

I tried to export it as package for event (Transactional messages ) in staging env and tried to import in prod. Import went successful however when i go to Settings >>  marketing Plans >>  Transactional messages >> event configuration , I do not see the Transactional messages that i imported. The log looks clean for package import as shown below... 

 

Installation of packages successful.
Package 'Transactional email 1': Saving entities of type 'xtk:cusResource'...
Package 'Transactional email 1': Saving entities of type 'xtk:packageDef'...

 

Any guidance ? 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by shelly-goel

Hi @ssoni-2 

Two things you can validate:
1. Exporting the "Transactional message" along with the "Event configuration" like below

and your import logs will look like this:

2. Once the import is successful, go to the imported event configuration and "publish" it so that the transactional message is linked to it and appears on the left side

Thanks

2 replies

Sukrity_Wadhwa
Employee
January 5, 2021

Hi @ssoni-2,

Was the given solution helpful to resolve your query or do you still need help with your query? Do let us know.

Thanks!

Sukrity Wadhwa
shelly-goel
shelly-goelAccepted solution
Employee
December 17, 2020

Hi @ssoni-2 

Two things you can validate:
1. Exporting the "Transactional message" along with the "Event configuration" like below

and your import logs will look like this:

2. Once the import is successful, go to the imported event configuration and "publish" it so that the transactional message is linked to it and appears on the left side