Question

Automatic Task Duration?

Is there a way to make the Duration of a task be automatically set to begin at the due date of the previous task and end at the current task due date?

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

3 replies

kynabaker16
Employee
May 1, 2020 4:41 PM UTC

Thank you for sharing these, Heather!

Translate
Level 4
Apr 30, 2020 6:23 PM UTC

Check out the Task Tracking Mode "Predecessor" It might do what you're looking for.