Batch Entry of Tasks Into a Workfront Project?

  • November 2, 2022
  • 1 reply
  • 1167 views

We have 30-40 tasks entered daily into a project to manage label production orders and printing. Most of the information is associated with custom fields.

Can I create a daily set of tasks by importing data from another system (Navision) or importing from intermediate spreadsheet?

Best answer by Doug_Den_Hoed__AtAppStore


Hi @quarkmage,

 

Yes, you can insert Tasks into Workfront from Excel data using the native Kickstart functionality (search for that keyword for details and examples), or to insert and update, using our Excel Updater solution (including custom data).

 

Regards,

Doug

1 reply

Doug_Den_Hoed__AtAppStore
Doug_Den_Hoed__AtAppStoreAccepted solution
New Participant
November 2, 2022


Hi @quarkmage,

 

Yes, you can insert Tasks into Workfront from Excel data using the native Kickstart functionality (search for that keyword for details and examples), or to insert and update, using our Excel Updater solution (including custom data).

 

Regards,

Doug

quarkmage
quarkmageAuthor
New Participant
November 2, 2022

Thanks. I will start with the Kick-starts data importer tools.