Bulk edit tasks to 100%

  • June 8, 2022
  • 1 reply
  • 542 views

I have multiple projects in a program that I can't bulk edit because the tasks in those projects aren't 100% complete. Is there a way to bulk edit those tasks to 100%?

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

RandyRoberts
New Participant
June 8, 2022

Yes, in a task report filtered for the tasks you're targeting.