Business days and non-business days in same project | Community
Skip to main content
Level 4
Feb 24, 2020 11:02 PM UTC
Question

Business days and non-business days in same project

Hello, This might be crazy to ask but I wanted to check. Is there a way to have some tasks be based off of business days, and some tasks to not be based off business days in the same project? Thanks! Tim Tim Brooks Invicro
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

jrieth
Level 3
Feb 26, 2020 12:00 AM UTC
Nothing straightforward that I know of. You might try creating a schedule where every day is a working day, and then creating an exception for every weekend except the ones that you want to work. ~Jeff Jeff Rieth