We have to put part of a project on hold but the other part is going ahead? What do you do in this situation?

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
RandyRoberts
RandyRobertsAccepted solution
New Participant
Jun 21, 2021 11:55 PM UTC

It depends on the predecessors. The short answer is I separate those tasks from the others by removing predecessors that point to the tasks that will still be worked on, then I put a dummy task in that is set to a really long duration (whenever you think it will be resumed) and have all the "on hold" tasks rely on the dummy task.

Something like

Dummy Task Duration 90 Days (or whatever)

Task 1 Predecessor set to Dummy task

Task 2 Predecessor set to Task 1

Task 3 Predecessor set to Task 2

When I want to resume, I set the dummy task to Complete and that triggers the Task 1 to start.

2 replies

RandyRoberts
RandyRobertsAccepted solution
New Participant
Jun 21, 2021 11:55 PM UTC

It depends on the predecessors. The short answer is I separate those tasks from the others by removing predecessors that point to the tasks that will still be worked on, then I put a dummy task in that is set to a really long duration (whenever you think it will be resumed) and have all the "on hold" tasks rely on the dummy task.

Something like

Dummy Task Duration 90 Days (or whatever)

Task 1 Predecessor set to Dummy task

Task 2 Predecessor set to Task 1

Task 3 Predecessor set to Task 2

When I want to resume, I set the dummy task to Complete and that triggers the Task 1 to start.

Translate
HeidiS1Author
Level 3
Jun 22, 2021 1:12 PM UTC

thank you so much