If you don't see any "open" tasks or issues/requests on your project, add a column for Status to your task and issue list views. You may have a task or issue that is marked 100% but has a status of Complete - Pending Approval.
If you don't see any "open" tasks or issues/requests on your project, add a column for Status to your task and issue list views. You may have a task or issue that is marked 100% but has a status of Complete - Pending Approval.
Can also be cause by date conflicts (as we just found out): make sure the end date of a task is after the start date (and also not the exact same time).
Another cause is if a parent task was originally a child task and for whatever reason had time against it, assignements, or is maybe just gitchy. Recalculate usually fixes these.
Also make sure all parent tasks are aggregating properly: that all child tasks being 100% also causes the parent to be 100%.
We've been running into these more frequently lately. We don't know if these are new habits, or the system being pickier now about bad existing habits.