Can you adjust the assignee's allocation in a task so you can assign 2 people to one task and have the work divided the way I want it- i.e Art director- 5%- Designer 95%. | Community
Skip to main content
Level 2
May 14, 2020 5:21 PM UTC
Question

Can you adjust the assignee's allocation in a task so you can assign 2 people to one task and have the work divided the way I want it- i.e Art director- 5%- Designer 95%.

Can you adjust the assignee's allocation in a task so you can assign 2 people to one task and have the work divided the way I want it- i.e Art director- 5%- Designer 95%. I want both to be aware of the timelines and due dates but don't have to have individual tasks.

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

3 replies

Employee
May 15, 2020 6:33 PM UTC

Hello Julie,

What you're looking for can be accomplished by switching your duration type to Effort Driven.

Here's our help article that details how to use it:

https://one.workfront.com/s/article/Effort-Driven-Duration-Type-122999470

Best of success!

Translate
Heather_Kulbacki
Level 2
May 15, 2020 12:13 PM UTC

You can also get in to edit that right from the Assignments column by clicking the icon in the corner of the assignments box.

Translate
Level 10
May 15, 2020 11:44 AM UTC

This is already available under [select task] » Edit » Assignments.

Just be aware that like the task itself, the percentage split is not a hard split: the system will do nothing to stop any assigned party from going over-allocation/budget.