Export Project to PDF - Add Task Numbers | Community
Skip to main content
Level 10
Mar 15, 2017 3:14 PM UTC
New

Export Project to PDF - Add Task Numbers

When exporting a project to PDF, there is no column for task numbers.

You currently can't determine on that PDF to which task predecessors corresponds to, making the PDFs almost useless as they are.

4 replies

Level 2
Apr 2, 2018 7:49 PM UTC

While the task number can be optionally added outlined, suggest that it be the default for any PDF print. This would be consistent with the on-screen view and would be a uniform user experience. We find that users find it confusing that what they see in the on-screen view is not the same as in he PDF created.

Translate
Level 10
Nov 22, 2017 8:21 PM UTC

Thanks @Chris for the info. At the time, in March, I always had the task number in my view when I exported but the task number never showed. This issue must have been fixed since then. Glad to know now it's been resolved.

Translate
Level 2
Nov 22, 2017 7:08 PM UTC

Actually you already to that. You need to add "Task Number" to your view. It does actually add an additional column to the UI view since it already shows, but it then adds the column to the export.

Translate
Level 2
May 11, 2017 7:45 PM UTC

Agreed, same issue for us.

Translate