Filter a project report by Days Since Entry

  • May 12, 2023
  • 3 replies
  • 794 views

Need help with filtering a report. I have a project report that shows me the days since entry and I'm trying to filter it to show me only projects that are < 60 days from entry, but I can't figure it out. 

Any feedback is appreciated!

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by skyehansen

hi, did you try reading the documentation here?

https://experienceleague.adobe.com/docs/workfront/using/reporting/reports/report-elements/use-date-based-wildcards-generalize-reports.html?lang=en

https://experienceleague.adobe.com/docs/workfront/using/reporting/reports/report-elements/understand-wildcard-filter-variables.html?lang=en

 

it felt like just doing "project / entry date / between / $$TODAY / $$TODAY-60d" should have worked. Am I misreading your question or perhaps you got an error we can help troubleshoot?

3 replies

MoniqueEvans
New Participant
May 16, 2023

I agree with @kundanism and @skyehansen. The other way you could write the filter is "project > entry date: Greater Than or Equal To: $$TODAY-60d" instead of a between statement

Kundanism
New Participant
May 16, 2023

@justinwa2 

Can you try this;

 

 

skyehansen
skyehansenAccepted solution
New Participant
May 12, 2023

hi, did you try reading the documentation here?

https://experienceleague.adobe.com/docs/workfront/using/reporting/reports/report-elements/use-date-based-wildcards-generalize-reports.html?lang=en

https://experienceleague.adobe.com/docs/workfront/using/reporting/reports/report-elements/understand-wildcard-filter-variables.html?lang=en

 

it felt like just doing "project / entry date / between / $$TODAY / $$TODAY-60d" should have worked. Am I misreading your question or perhaps you got an error we can help troubleshoot?