Fiscal Year Applied to all Gantt Views | Community
Skip to main content
New Participant
January 17, 2018
New

Fiscal Year Applied to all Gantt Views

  • January 17, 2018
  • 4 replies
  • 532 views

Workfront has done some great redevelopment of gantt chart functionality. The only (major) issue is that all gantt views whether in projects/portfolios or calendars are hard coded to calendar year.

Since my company (and many others) operate on a fiscal year, we are unable to use any of the new gantt functionally as it would really confuse executives and users.

The only workaround is to quickly zoom to the moth view to get quarter and year headings to disappear - very unfortunate considering how good this tool could be.

An interesting solution would be to allow custom quarters to determine the date range presented on all gantt views.

Please vote. Thanks!

Steve

4 replies

New Participant
July 31, 2025

We've wanted the ability to view custom fiscal years & quarters in gantt charts for years. Still not available functionality sadly.

New Participant
July 31, 2025

Is there any possibility that the gantt charts can use custom quarters? The gantt charts are nice, but without the option of fiscal year quarters, they aren't very useful to my organization since we use fiscal year.

New Participant
October 14, 2021

I am looking for this functionality too. We run projects by around our fiscal year and calendar year. We need to be able to update our instance to reflect our fiscal quarters by dates.

New Participant
September 5, 2019

This functionally would seem to be a day one item, no? Especially since Workfront is an Enterprise focused tool and many companies run on a fiscal calendar.