Hello! I am trying out the Workload Balancer but can anyone tell me why hours for tasks that are completed are showing for the workers?

No text available
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

2 replies

imgrund
Employee
Oct 9, 2020 2:20 PM UTC

Highly recommend turning on the Projected Dates (the enhancement Heather mentioned) as that will show if something ended early or if something will most likely be delayed because the rest of the project is running late. My Creative and Dev resource managers love that since they don't usually have instead in how the project is doing until it gets to them. So totally helps with prioritizing work.

Translate
Heather_Kulbacki
Level 2
Oct 9, 2020 11:56 AM UTC