Help with "Predecessor Complete" = Yes when the predecessor is not complete | Community
Skip to main content
New Participant
April 30, 2025
Solved

Help with "Predecessor Complete" = Yes when the predecessor is not complete

  • April 30, 2025
  • 1 reply
  • 323 views

I found that the “Predecessor complete” is showing Yes when a predecessor is not complete, here is an example of that on a project:

Project = https://barclaysus.my.workfront.com/project/67ec012623b06b3f9d1b5d8eb0506c2d/tasks

Here is a screenshot, where I brought in “Predecessor Complete” and “Can Start”

 

Can you please help us understand why Predecessor Complete = Yes when it is not ready to start?

Are we missing something on this one?

 

 

 

Thank you for your help!

Best answer by skyehansen

we don't have a Predecessor Complete field. Is this a custom field on your side, or a calculated column? If so, what does it relate to?

1 reply

skyehansen
skyehansenAccepted solution
New Participant
April 30, 2025

we don't have a Predecessor Complete field. Is this a custom field on your side, or a calculated column? If so, what does it relate to?