Help with task ordering

We want to reorder the Task Statuses, but the order we shift them to on Setup>Project Preferences>Statuses. We can do that just fine, but the order is not reflected in any user's experience, no matter what Group they are in.

What trick are we missing?

We are escalating to Support but wanted to mine this site as well for answers, thanks!

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

5 replies

Level 4
May 9, 2022 4:23 PM UTC

We had this issue last week actually, with request statuses. When I escalated to Support, they asked me to try reordering statuses under Project Preferences and under Groups, try a different browser, and clear my cache and cookies... none of that worked! Now they are looking for a code fix for this and said they would get back to me early this week. Sounds like it's a wider issue than just our instance.

Translate
Heather_Kulbacki
Level 2
May 2, 2022 12:29 PM UTC

I also like to go to the Group > Statuses rather than Project Preferences > Statuses, that seems less confusing to me.

But remember each user is going to see statuses in a different order depending on what group is assigned to the project they are looking at, regardless of which group that user belongs to.

Translate
RandyRoberts
New Participant
May 2, 2022 2:30 PM UTC

That's good to point out. It's a subtle but meaningful difference.

Translate
RandyRoberts
New Participant
Apr 29, 2022 5:05 PM UTC

I had (and still do) some problems understanding this area. I

I went to each group and set the statuses the exact same way and then went to "system statuses" and set them up the same way.

They seem to work now (sorta) but I still don't understand exactly what the rules are.

Translate
skyehansen
Level 4
Apr 28, 2022 8:10 PM UTC

in the setup area, which group are you reordering the statuses in, and what is the group of the project set to (that the tasks are in)?