How can I set a default task constraint for all tasks to be Fixed Dates with simple duration?

  • April 30, 2020
  • 2 replies
  • 598 views
No text available
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

2 replies

imgrund
Employee
May 1, 2020

Hi Howard - Yeah, to get fixed dates, you just need your Project Owners to adjust both the start and end dates of the tasks. We have a "one-off" project for resourcing, and as long as you touched both those fields, the task constraint changes.

Heather_Kulbacki
New Participant
May 1, 2020

HI Howard,

In Setup > Project Preferences > Tasks & Issues you can set the default duration type to Simple. But unless you're creating project templates where all the tasks have a constraint of Fixed Dates, I don't believe there's a way to set a default constraint.