How do you filter projects on the Workload Balancer?

My team has projects that are in on hold and dead statuses, but they are still showing as taking up time on the workload balancer.  Does anyone know how to filter these out?

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

2 replies

Level 5
Aug 29, 2022 10:13 PM UTC

You can set up a filter (for unassigned you'll need to click on the carat next to the words and then the filter icon should appear.  For assigned work it the filter icon is to the right of the words.  You can set up a filter for project status not equal to dead or on hold to filter those out.

Translate
Level 3
Aug 30, 2022 12:25 PM UTC

Perfect thank you!  FYI you also need to click the stack filters slider if you have other filters active.