How to calculate turn time from request entry date to project completion?

  • April 25, 2022
  • 2 replies
  • 1496 views

Hello! I am looking to build a report with a column that calculates the overall turn time from the Request Entry Date to the Resolve Project's Actual Completion Date - excluding weekends and holidays.

Any help is appreciated :)

Thank you!

Best answer by Richard_Le_

Hi Kasey,

Use the following text mode to calculate the turnaround time from request entry to project completion.

displayname=Turnaround TIme

textmode=true

valueexpression=ROUND(DIV(WORKMINUTESDIFF({convertedOpTaskEntryDate},{actualCompletionDate}),480),0)

valueformat=HTML

The expression looks at the number of working minutes between the two dates and divides the number of minutes by 480 which is the number of minutes in a standard 8 hour working day. This gives you the total number of days exluding any non working time such as weekends or holidays.

Best Regards,

Rich.

2 replies

Richard_Le_Accepted solution
New Participant
April 26, 2022

Hi Kasey,

Use the following text mode to calculate the turnaround time from request entry to project completion.

displayname=Turnaround TIme

textmode=true

valueexpression=ROUND(DIV(WORKMINUTESDIFF({convertedOpTaskEntryDate},{actualCompletionDate}),480),0)

valueformat=HTML

The expression looks at the number of working minutes between the two dates and divides the number of minutes by 480 which is the number of minutes in a standard 8 hour working day. This gives you the total number of days exluding any non working time such as weekends or holidays.

Best Regards,

Rich.

New Participant
April 27, 2022

Thank you so much, I will give this a try! Would this work best on a Project or Request report?

New Participant
April 27, 2022

No problem Kasey.

This will only work on a Project report.

ElenaDooley
New Participant
April 26, 2022

I have a project report that does just that! Try this text mode... I don't know how to exclude holidays, though.

displayname=Response Time Request Entry to Project Completion

textmode=true

valueexpression=WEEKDAYDIFF({convertedOpTaskEntryDate},{actualCompletionDate})

valueformat=HTML