Hi,

 

to create a child / subtask, you just need to add the field parentID to your Create Record module and map the id of the parent task to it.

 

Regards

Lars

1 reply

lgaertner
lgaertnerAccepted solution
New Participant
March 21, 2025

Hi,

 

to create a child / subtask, you just need to add the field parentID to your Create Record module and map the id of the parent task to it.

 

Regards

Lars

New Participant
March 21, 2025

If I want to create sub task under sub task, is it same way to map?

lgaertner
New Participant
March 21, 2025

Correct, the "sub sub task" would get the sub tasks ID mapped to the parentID field.