How to filter for "Min" task number?

Looking for syntax (presumably in text mode) to add a filter to a task report to only display the minimum open task number for a project.

Example:

A Project has 5 tasks:

Task 1 - Complete

Task 2 - Complete

Task 3 - Open

Task 4 - Open

Task 5 - Open

I want to return only Task 3 (the lowest open task). In SQL, I would use the MIN() function to do this. Is there something similar using Workfront's text mode syntax?

Thanks!

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Doug_Den_Hoed__AtAppStore
Doug_Den_Hoed__AtAppStoreAccepted solution
New Participant
Nov 30, 2021 6:29 PM UTC

Hi Keegan,

Assuming these tasks are chained (e.g. Finish-to-Start), you could check for Percent Complete < 100 and Handoff Date Not Blank to then retrieve only Task 3.

Regards,

Doug

2 replies

Doug_Den_Hoed__AtAppStore
Doug_Den_Hoed__AtAppStoreAccepted solution
New Participant
Nov 30, 2021 6:29 PM UTC

Hi Keegan,

Assuming these tasks are chained (e.g. Finish-to-Start), you could check for Percent Complete < 100 and Handoff Date Not Blank to then retrieve only Task 3.

Regards,

Doug

Translate
KeeganWaAuthor
Level 2
Dec 1, 2021 3:41 PM UTC

This appears to do the trick. Thanks so much @Doug Den Hoed‚ !