In a Project report, can I highlight in red the date of the Planned Start Date if it is late AND the project is not Current?

I currently have conditional formatting that highlights the Planned Start Date if it's late, but we don't want it highlighted once the project starts. The idea is to alert our clients that they have not given us what we need to start the project by our agreed upon date. I attached a screenshot to help.

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Doug_Den_Hoed__AtAppStore
Doug_Den_Hoed__AtAppStoreAccepted solution
New Participant
Nov 21, 2020 2:31 PM UTC

Hi Jennifer and Samantha,

Conditional formatting rules are evaluated top to bottom, applying the rule that is true, so i suggest you:

  • first check for the Project Status = Current and set Planned Start Date background to white (effectively “ignoring” it), then
  • second (ie “otherwise”) check if the Planned Start Date is less than $$NOW then set it to red (ie “take action”)

Regards,

Doug

3 replies

Doug_Den_Hoed__AtAppStore
Doug_Den_Hoed__AtAppStoreAccepted solution
New Participant
Nov 21, 2020 2:31 PM UTC

Hi Jennifer and Samantha,

Conditional formatting rules are evaluated top to bottom, applying the rule that is true, so i suggest you:

  • first check for the Project Status = Current and set Planned Start Date background to white (effectively “ignoring” it), then
  • second (ie “otherwise”) check if the Planned Start Date is less than $$NOW then set it to red (ie “take action”)

Regards,

Doug

Translate
Level 2
Nov 23, 2020 5:48 PM UTC

Thanks Doug! I really appreciate your help!

Translate
SamanthaIsin
Level 7
Nov 20, 2020 6:34 PM UTC

Would also like an answer on this for the use of applying a combination of automation rules to columns!