Feb 1, 2021 8:50 PM UTC
Question

Is there a limit to the number of entries on a user's timesheet? If so...what is it? Is it configurable? Are there any workarounds?

No text available
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

3 replies

ChrisBudgen
Level 5
Mar 18, 2022 12:34 PM UTC

A couple of weeks ago I stumbled across this thread: https://one.workfront.com/s/question/0D70z000006kxbqCAA/detail and we have since then had our limit set up to 250.

Translate
Level 2
Mar 15, 2022 3:45 AM UTC

There is a hard limit of 45 most recently updated jobs that appear on ones timesheet. I hear they’re looking into getting it increased, but it has yet to happen. Use the thumbtack to pin the important ones so they always stick around.

Translate
ChrisBudgen
Level 5
Feb 10, 2021 7:55 PM UTC

When on-boarding a new subsidiary we add accumulated history data for all migrated projects on the timesheet of a Dummy User. The only limitation we encountered was that a single entry cannot have more then 1000 hours on it. Our work around was to create different task time types and booking 1k per task-type/day/task combination. You could also put it on different days or different tasks.

Our record timesheet has 92k hours on it ;-)

Translate