New Participant
Feb 10, 2025 9:42 PM UTC
Question

Linking Predecessors by Choosing Tasks

This was something that I could do in Workamajig but I don't believe you can in Workfront. I want to select multiple tasks and 'link' them together so it automatically assigns the predecessors to new tasks based on the workflow. Is this a functionality the Workfront has that I'm missing?

3 replies

skyehansen
Level 4
Feb 11, 2025 8:06 PM UTC

No. I don't have Workamajig, but assuming you want to select 10 tasks and then click one button to automatically assign predecessors between them, or to new tasks following them, this is not how Workfront works. You'll need to manually assign them on a task by task basis.

Translate
RaeBe1Author
New Participant
Feb 11, 2025 9:55 PM UTC

Yes, is it something that might be looked into? Thanks!

Translate
skyehansen
Level 4
Feb 11, 2025 10:41 PM UTC

Probably the quickest way for it to be "looked into" is -- I'm going to ask that you go to this link and click on the "share an idea" blue button.

https://experienceleaguecommunities.adobe.com/t5/workfront-ideas/idb-p/workfront-ideas

 

reason being that there's a specific format they would like you to post with -- you'll need to answer the four questions below.

 

Description -

Why is this feature important to you -

How would you like the feature to work -

Current Behavior -

Translate