We just had someone cancel the project that contains about 20 of our critical request queues.

It would be great to be able to create a queue on its own and then associate it with projects (like custom forms).

3 replies

New Participant
June 26, 2019

We created a template (with no tasks on it- so its just a shell of a template) that has all the needed RQs attached to it. Our PMs are instructed to attach this template to every project they open, and then they can create issues/requests for whatever they need (eg, Studio Spec Sheet, Art BUying, etc) and its tied to their project.

New Participant
July 26, 2017

Make it a point to remove "delete" from the project options. We do this for a variety of projects in order that they do not delete critical work.

New Participant
March 31, 2017

Agreed. We have actually implemented something similar to what you're looking for but something like a backlog at the Project, Program, and Portfolio level would really helpful. Ideally a Portfolio backlog that would be filtered down for Programs and Projects. Especially for requests, this would be nice.