Is it possible to mark task work complete if you only have Light license level?  Is this only possible if you have a Standard license level even if you have manage or contribute access to a project? 

Best answer by Daniel_Clarke

@bethholzman you are correct, Light users cannot mark work complete.

Access level documentation includes this note:

"Users with the Light access level:

  • Can be assigned work items but can’t complete them."

Forces users who will be actively working on projects into the Standard License type.  

1 reply

Daniel_Clarke
Daniel_ClarkeAccepted solution
New Participant
January 13, 2025

@bethholzman you are correct, Light users cannot mark work complete.

Access level documentation includes this note:

"Users with the Light access level:

  • Can be assigned work items but can’t complete them."