Question

Milestone Reporting

  • December 5, 2019
  • 14 replies
  • 2490 views
Does anyone have milestone reports that they use regularly and what sort of data is used and how is it used? We are starting to put Milestones on to the creative projects but besides the view to see all the dates in a list with the projects what else are companies using them for? Kimberly Rea Schneider Electric Solutions Manager
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

14 replies

New Participant
December 6, 2019
I use milestones to make calendars (though the calendars have other issues).
Kundanism
New Participant
December 6, 2019
Hi Skye, When calculating the difference, have you used text mode. Since I am also looking such guidance, I used it before but missing some info. Thanks and Regards Kundan. Kundan Kumar KGON (Kverneland Group Operations Norway AS)
New Participant
December 6, 2019
Hi, Skye could you please advise what are you pulling to this milestones report? one of my manager is looking to display milestones completed late but I've never build that type of report. Thanks Marta Marta Sowa
New Participant
December 5, 2019
we're using them hand in hand with the baselines functionality to be able to track issues with milestone planned dates moving once we've started the project. By calculating the difference between the original planned completion date and the one we had to change it to (to accommodate the project timeline), we can chart how late various milestones are hitting and better speak to where the roadblocks are. (e.g. Creative review milestone always has to get changed: do reviewers know when to stop reviewing?) -skye