Skip to main content
Level 2
April 11, 2024
Question

Navigating Workload Balancer

  • April 11, 2024
  • 2 replies
  • 539 views

Is there a way to change the order of projects under a user in Workload Balancer? I tried looking at documentation and could not find how the order was established. It is not alphabetical or by largest hours per project.

2 replies

KellieGardner
New Participant
April 11, 2024

These are the only sorting options I'm familiar with:

 

 

If you enter Project Name in Projects By it should sort them by project name, if you put project planned start date it should do it by that date, etc.

 

 

Level 2
April 15, 2024

Thank you! After looking into this, I was hoping there would be an option to sort by task planned hour. I can sort by project planned hour, but not task. Thank you for pointing me in the right direction.