Negative Lag time issue with notifications | Community
Skip to main content
Level 3
April 2, 2025
Question

Negative Lag time issue with notifications

Hi,
We have our projects set up with negative lag time for all tasks, since we need to work off of a certain Launch or Send date. Now we run into the issue, that the assignees of e.g. Task 2 do not get notified anymore, since the predecessor in the list starts on e.g. Task 1 Predecessor = Task2 - 5days. Any ideas how we can have a proper workback form a Launch date where all tasks lead up to, but the notifications will still work?

1 reply

Doug_Den_Hoed__AtAppStore
New Participant
April 2, 2025

 

Hi @trakill,

 

I explain one approach I've used in my Get A Handle On Project Start Dates blog post, which might give you some ideas.

 

Regards,

Doug

Translate