So, as we turn more and more projects to "On Hold" status before finally killing them when the apocalypse arrives, I've had this new experience where the Proof that we were in the midst of working on started spitting out Late Notifications to everyone reviewing the proof AFTER I turned the project from Current to On Hold. Why oh why Workfront would you do that? What could be the logic? Jill Ackerman

2 replies

JillAcAuthor
New Participant
March 23, 2020
Hi For me, it's the system default On Hold, no special settings.
New Participant
March 23, 2020
I think you need to check what status your "on hold" equates with. I think we had to create our own version of a hold status to stop people from being able to bill time to the project, get notifications, etc. I'd start there! Good luck on all fronts - Erica Erica Baitler VP, Operations precisioneffect