Planned completion date - a break down per task in an issue?
I think I know the answer but wanted to pose it to the community to see if anyone has any other ideas / suggestions.
One of my teams are under resourced:
- They have many requests sitting in a queue.
- They don't don't want to convert requests into project based on the teams work load / time availability
- They have 3 different job functions working on each request (copywriter, designer, translator) who are all working on the 1 planned completion date that pulls though on the issue despite all having different durations to finish their individual tasks.
QUESTIONS:
1. Is there any way to break down the planned completion date? (without converting it into a project)
2. Has anyone encountered something similar and have advice on how to manage this so they can all work to an individual deadline on an issue?
Thanks as always