Planned Hour Distribution
Hi everyone, I'm currently working on project templates and I'm struggling with the way WF distributes planned hours evenly across the task duration. Is there a way to stop this from occurring and instead fill an assignees working day with as much of a task's planned hours as possible? For example, standard working day is 7 hours, a task has 8 planned hours and a duration of 2 days. At the moment WF splits the task over 2 days, 4 hours in each of the two days rather than 7 hours in day 1 and 1 hour in day 2.