Planner and zero hour project lists

Is there a way to remove projects within the current view of the Planner if the user has zero hours allocated within that timeline (of the current view)?

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

3 replies

Kundanism
Level 10
Mar 13, 2023 7:24 AM UTC

Hi @danaherman 

Trying to understand, 

situation 1: is the projects having zero planned hours?.

situation 2: is the task with respect to user having zero planned hours?

Which is relevant?

 

Translate
New Participant
Mar 13, 2023 2:32 PM UTC

Hello, thank you for your reply!

 

Most often I find that it is situation 2, but both are relevant in that the Planner is listing A LOT of projects for users, and many have zero hours allocated toward them within the timeline I'm trying to view (perhaps there are hours on the task outside of the timeline I'm currently viewing, either in the past or future), and I'm curious if there's a rule to exclude projects with zero hours allocated within the given view.

Translate
New Participant
Mar 15, 2023 7:42 PM UTC

@kundanism - Sorry, forgot to tag you in my above reply. Any thoughts?