For those that bill the hours entered on a project, how do you handle when a resource works overtime on the project to get the actual cost of those hours on the project? 

For example - if an hourly resource with a cost of $20.00 / Hour works 10 hours on a project, with 2 of those hours being overtime, how do you get the actual cost to be $220, rather than $200.

 

I'm hoping someone has a "solution" for this that they have been using and will share. 

 

Thanks, 

Alex

1 reply

KellieGardner
New Participant
October 6, 2025

Overtime is not calculated by default in Adobe Workfront, but you can create a Timesheet report that calculates overtime.

 

View: Calculate Overtime Cost in a Timesheet View | Adobe Workfront