Project % Complete showing 0% when half of tasks marked Complete/100%

  • October 15, 2018
  • 11 replies
  • 1870 views

Has anyone run into a situation where you've completed a larger number of tasks within a project but, at the project lst level, the % Complete still shows 0%? Chris Watson KVH Industries, Inc.

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

11 replies

Level 2
October 15, 2018
Hi Chris, I can't tell from your screen shot, but is it by chance that you don't have the child tasks under that first one? Cathy Glenn TRTA Marketing