Project Completion Date after re-opening a project

  • June 3, 2025
  • 2 replies
  • 329 views

Hello,

When a project is completed in Workfront but then moved back to "current" (re-opened) again, the completion date remains. Is there a way to turn that off so that the completion date is removed when the project is re-opened?

Best answer by Madalyn_Destafney

A project's completion won't ever be removed. The idea is when you reopen the project to add necessary tasks that made you reopen the project in the first place, your completion date will change to be the latest due date of the new tasks you've added/existing task dates you've adjusted. 

2 replies

kautuk_sahni
Employee
July 16, 2025

@natashava Just checking in — were you able to resolve your issue?
We’d love to hear how things worked out. If the suggestions above helped, marking a response as correct can guide others with similar questions. And if you found another solution, feel free to share it — your insights could really benefit the community. Thanks again for being part of the conversation!

Kautuk Sahni
Madalyn_Destafney
Madalyn_DestafneyAccepted solution
New Participant
June 4, 2025

A project's completion won't ever be removed. The idea is when you reopen the project to add necessary tasks that made you reopen the project in the first place, your completion date will change to be the latest due date of the new tasks you've added/existing task dates you've adjusted. 

If this helped you, please mark correct to help others : )