Skip to main content
New Participant
October 22, 2020
Question

Project Condition Trend Report

  • October 22, 2020
  • 5 replies
  • 1218 views

Hi all! I'm trying to create a trend report that shows a week over week comparison of active project conditions - the number of Current, At Risk, In Trouble projects, week to week. Given that Workfront doesn't keep historic data, this may not even be possible, but I thought I'd check with the experts. Has anyone had any luck with a similar report?

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

5 replies

New Participant
October 22, 2020

Hey James!

We actually started capturing historical data back in 2018. The first way we have surfaced that has been in showing historical conditional change on a project. This is in the enhanced analytics product that is for enterprise and business customers. It looks like this:To access enhanced analytics you can just update your layout template to show it.

Thanks,

Joel

New Participant
October 22, 2020

Joel, this is a great graph and have looked at it before, but how can I expand it to display all projects? For example -In your screen shot it says there are 13 projects but it only displays 7.

New Participant
October 22, 2020

Great question! The flight plan and activity charts have a scrollable y axis... so if you have your mouse inside the charts you can scroll up and down. It does cap at 50 projects at a time but pagination and ordering will be pushed out with the 20.4 release (that is included in my picture).

Thank you!

Joel