Projected Start Date, Planned Completion Date, and Projected Completion Date not calculating

I have a project with two tasks that are not calculating the Projected Start Date, Planned Completion Date, and Projected Completion Date. Those fields just list N/A. I have checked the start mode (which is set to Start Date) and constraint (which is set to As Soon As Possible). I can't figure out what else I'm missing that might be causing this. Anyone have an idea?

KellieGardner
KellieGardnerAccepted solution
New Participant
Jan 23, 2025 6:34 PM UTC

Check your update type and make sure it's not set to manual. If it's set to manual your project will only update when you tell it to.

 

Project Update Type overview | Adobe Workfront

2 replies

KellieGardner
KellieGardnerAccepted solution
New Participant
Jan 23, 2025 6:34 PM UTC

Check your update type and make sure it's not set to manual. If it's set to manual your project will only update when you tell it to.

 

Project Update Type overview | Adobe Workfront

Translate
DarcySm1Author
Level 3
Jan 23, 2025 7:03 PM UTC

That was it! Thank you!