Resources Overallocations for projects

  • January 25, 2024
  • 1 reply
  • 954 views

Hi Community,

Any idea why Workfront will be showing resources overallocations on the workload balancer when the resources is 100% allocated across two projects (i.e., 2977 is 25% and 2979 is 75%)?.  Jan 16.48hrs, Feb 16.05hrs, and March 16.05 hrs over allocations. please see screenshot below and your input is super appreciated. 

 

 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by _Manish_Singh

If you hover over the red box, it shows capacity vs planned hours for that period. That might give you a hint.

You should also consider checking User Schedule and Work Time (in user profile settings).

1 reply

_Manish_Singh
_Manish_SinghAccepted solution
New Participant
January 25, 2024

If you hover over the red box, it shows capacity vs planned hours for that period. That might give you a hint.

You should also consider checking User Schedule and Work Time (in user profile settings).