Question

Status Changes on Project

  • May 13, 2016
  • 71 replies
  • 7752 views
I would like to create a report that provides the dates or elapsed days between status changes on a project. For example, days between Current to Pending Approval, Pending Approval to Pending Implementation, Pending Implementation to Closed. We would like to identify where significant delays occur within projects occurred. Suggestions?
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

71 replies

Level 2
May 13, 2016

If you’re not talking about approval path timing, you should be able to get close by using the milestone view on a list of projects. This assumes you have 1) a milestone path set up that includes the different phase gates you want to track, and 2) you have aligned the project tasks to those milestone phases in the schedule.

Tim Golden