Task visibilty for multiple assignees, assigned Teams, and assigned Roles?
Hi all,
I'm looking for information on how task visibility works for assignees. To explain:
I have project managers in a dept who regularly assign 10-40 assignees to the same task. Their reasoning is that the task is shared, and they want their team members to each work on a portion of the task as able.
They don't want to assign using a Team, because they say when one person on the Team chooses to 'work on it', then the task disappears for everyone else - they want it to remain visible. This is our sticking point: allowing multiple persons to work on a task and have it remain visible to all until fully complete.
I am wondering if assigning to a Role produces the same behavior as assigning to a Team? Or if it will provide the visibility they are asking for. Or, if someone has solved for a similar situation and has insight? Our current process is playing havoc with reporting & resource managment, not to mention just being able to view the project task list.
Thanks! -Laura