Tasks assigned to multiple people to show up on both of their task reports

I have a project where every task is assigned to 2 different people as they both need to complete it. I have task reports for each of the users but the list of tasks only shows on one of their reports. (Assuming because her name is first in the alphabet) I have the same settings on both reports. Any way to get this to show up on both reports?

*this sounded familiar like I had read about in in this blog before BUT I searched and could not find it.

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

6 replies

Employee
Jul 29, 2020 10:14 PM UTC

Hi Tracy,

Assigned To means Workfront is looking at the owner.

Assignment Users means Workfront is looking at all assigned users.

Try adding that instead of Assigned To. =)

Translate
TracyPa2Author
Level 4
Jul 30, 2020 1:33 PM UTC

Thank you, that made it show up on all of their task reports, but it there a filter to make it not show if their part is done?

If not, I will rebuild the report as a task report.

thanks

Translate
Employee
Jul 30, 2020 3:12 PM UTC

I don't believe so, only a column for Assignments & Status.

Translate
Level 6
Jul 28, 2020 8:43 PM UTC

Hi Tracy! I've had the same issue in the past. If you create an Assignment report instead of a Task report, the task will show up on the report for both users.