Tasks - Default Duration Type Per Project/Portfolio?

  • June 15, 2023
  • 1 reply
  • 653 views

We share our Workfront instance with many other groups at our organization, and one of those groups has expressed interest in having the Default Duration Type for tasks set to Calculated Work (it's currently set to Calculated Assignment). Is it possible to do something with that default for that one specific group (like with a template or something at the Portfolio level), or is the only option to change it for the entire instance?

 

Thank you!

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by skyehansen

I feel like I'm missing something here... why wouldn't you unlock it and then switch over to the group and edit it for that group? Did I read your question correctly? (see screenshot)

1 reply

skyehansen
skyehansenAccepted solution
New Participant
June 15, 2023

I feel like I'm missing something here... why wouldn't you unlock it and then switch over to the group and edit it for that group? Did I read your question correctly? (see screenshot)

DerrickPoAuthor
New Participant
June 16, 2023

We haven't gone back and changed much with setup like that since implementation, so I honestly didn't know that was a possibility. Thanks very much for your help!