Tracking "on time" delivery

How are different organizations tracking "on time" delivery? What triggers start date and what triggers end date? How do you account for delays (reviews, changes in direction, etc)? 

2 replies

Srinija_N
Level 7
January 16, 2025

I would prefer to use the Planned/Projected/Actual Start and Completion Dates to see the difference and create a view/report with all these dates (and also some textmode field if I want to look at the variance)

 

For the reasons, you might have to use a custom field created on your form to capture the details. or just the Updates/Comments section

Translate
KELLYRE4Author
New Participant
January 21, 2025

Thanks! Is there a report type you recommend starting from? My goal is to show planned vs. actual completion date at 3 distinct tasks for all projects.