Hi All,
We bulk upload the majority of our learning product projects at the beginning of the year. When various assignees add PTO to their calendars after the projects are loaded, it's necessary to recalculate timelines to reflect the PTO (our projects use the 'Consider user time off in task durations' setting). I recently created a Fusion scenario that recalculates the timelines for active projects in our learning portfolios; that's working fine thus far.
My counterpart (who works with our creative projects) is thinking of adopting the automation for his portfolios, but he asked if a report could be generated to reflect what projects are impacted (and what the impact on the schedule is).
I don't see an obvious way of doing this. We do track Planned Completion Date for the Project object in our Updates Feeds. I created a Journal Entry report, and it tracks changes to the field that result from updates to the projects (e.g., when a task duration changes, causing the project's Planned Completion Date to change). It does not reflect when the field changes due to a recalculation from added PTO (or presumably an added holiday/exception, if one is created later in the year).
The closest thing I can get is to compare when the Planned Completion Date for the most recent journal entry record does not match the current Planned Completion Date for the project (see the screenshot for my sample project). However, I'm unsure how to limit the report to the most recent entry, and the report only identifies the discrepancy (not the source--specific user PTO, holiday, etc.).
Has anyone come up with a way to track new PTO records and their impact on project schedules? Thanks.