Solved
Update custom form based on tasks completed
We have a custom form that feeds a report for our stakeholders to know the status of the project. The % complete is not a clear indicator of the phase of our work/the project. Right now updating the status field in the form is manual and not tied to anything. We want to select specific tasks (mile makers) to be tied to the custom for to update the "status" field as they are completed. Is this possible? Alternatively, is there a way to add the "status" field as a column that can be viewed AND updated in the project view? So then, as we complete the mile marker tasks we can also update the status? I was able to add it as a column but am not able to edit while marking a task as complete. Thanks!