I had a large MSM rollout that began to encounter errors. Is it possible to cancel a rollout that is underway without restarting the author instance? Are there any useful management tools in the osgi console or JMX console related to rollouts?

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Peter_Puzanovs
Peter_PuzanovsAccepted solution
New Participant
Jun 27, 2019 9:17 AM UTC

Hi Andy,

The tools to fix MSM when something goes wrong are somewhat limited. Have asked this question to Adobe Engineering team continuously, have not heard definite answer on this yet.

Best possible way here:

Wait till it finishes rollout

Restarting can screw up AEM MSM index and leave you in a worse state then you started with.

Regards,

Peter

1 reply

Peter_Puzanovs
Peter_PuzanovsAccepted solution
New Participant
Jun 27, 2019 9:17 AM UTC

Hi Andy,

The tools to fix MSM when something goes wrong are somewhat limited. Have asked this question to Adobe Engineering team continuously, have not heard definite answer on this yet.

Best possible way here:

Wait till it finishes rollout

Restarting can screw up AEM MSM index and leave you in a worse state then you started with.

Regards,