Simulating Wait step choices using Date Tokens and date math

The post title is a bit of a mouthful, but if you've been bitten by a certain feature gap you'll know what I mean.

 

One of the first things you learn about Wait steps is they don't have a literal Add Choice option.

nelson pointing at marketo

 

This can be frustrating when you want to vary the Wait delay based on  runtime conditions (that is, conditions you can’t know until the person has qualified and entered the flow) importantly including no delay at all.

 

But with a tiny bit of work, you can simulate Wait step choices.

 

It’s a matter of managing a Date/DateTime field, earlier in the same flow, using Marketo’s simple plus/minus support.

 

Here’s such a field:

 

field mgmt

 

And here’s a flow that uses that field to manage a subsequent Wait step:

 

flow steps

 

This approach works because of 3 convenient truths:

 

  • Change Data Value is synchronous within a single flow[1]
  • Date tokens understand a few math operators
  • Wait steps using a Date token will be skipped if the Date token is empty

 

Truth be told, I don't always endorse this tack over multiple Smart Campaigns. Whatever’s making you want drastically variable Wait periods (other than implicitly variable periods like wait-until-anniversary) may mean the lifecycle is going to differ in other ways as well, in which case discrete SCs help you keep your sanity. But it's there if you want it.

 

P.S. Yes, you can also use a Number {{my.token}} for the delay itself, a setup that might be almost too cool to follow! Or a Text {{my.token}} (don’t know why you’d choose this over Number, though) as long as you don’t include the unit  (“days”, “hours”) in the value, keep that hard-coded in the Change Data Value box.

 



Notes
[1] “Synchronous” meaning the New Value is guaranteed to be readable in the next flow step. Contrast this with, for example, webhook-based updates, which are asynchronous (background) value changes.

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

13 replies

SanfordWhiteman
Level 10
November 28, 2019

That's not the way the method in this blog post works.  Per the method above:

  • Create another Date field, Next Follow Up Date
  • Set Next Follow Up Date field to Lead Creation Date + 55 days (using Change Data Value)
  • Wait until Next Follow Up Date
Translate
Vidhi_Kare
Level 3
November 28, 2019

Hi @Sanford Whiteman‌,

That is so good that my questions are already listed in the community.

Just confirming one doubt actually.

If i am using Date Time Token in Wait step and adding  x days to Lead Creation date to send the next email, will this work fine as Lead Creation Date is different for each lead obviously.

Thank you,

Vidhi

Translate
SanfordWhiteman
Level 10
July 16, 2019

Date tokens only ever work in triggers, so that's to be expected.

Translate
Diego_Lineros2
Level 5
July 16, 2019

I have a text token with this format 16 Jul 2019 12:00 UTC then I have a data change step like this {{my.texdatetoken}} - 2hours , then the waiting step. The calculation is correct and it works as trigger, not as batch because I get the same error than Jay Jang

Translate
Diego_Lineros2
Level 5
July 16, 2019

This is somenthing very interesting, if it is a trigger campaign, it works for me, if it is a batch campaign doesn't take the datetime token.

Translate
Ariel_Sasso
Level 3
July 8, 2019

Awesome information as always!!!

Translate
Ariel Sasso
Jay_Jiang
Level 10
July 8, 2019

Tried

How did you get the wait step to finish on a specific hour and minute when you can only use date tokens and pick an time on the hour?

Translate
SanfordWhiteman
Level 10
July 7, 2019

Nope, it works with minutes and datetimes just fine. You must not have tested correctly: I have tokenized waits of 5, 10, 20 minutes running with the method described here.

Translate
Jay_Jiang
Level 10
July 7, 2019

Unfortunately wait steps don't take dateTime tokens which are accurate to the minute/hour.

Currently, the only way I've found to incorporate wait choices down to minutes/hours inside Marketo only is to use request campaign, where the request campaign in your flow has choice logic and the requested campaigns have different wait step durations.

You will need to split your campaign into sections. As an example, a typical campaign might need to be split into 3 sections:

1. first part of your campaign flow

2. choices of wait lengths

3. rest of your campaign flow

So at the end of (1) you request one of many (2) and in each one of (2) there's a wait step and the last flow step to request (3)

Translate
SanfordWhiteman
Level 10
July 6, 2019

I actually need to re-answer your question above as I read it too fast.

The delay {{my.token}} (if you choose to use one) is used in the Change Data Value, not in the Wait.

Translate